Rapid HVAC upgrade gives Carrier the Edge

f9ea22c3-0f01-4cdc-b146-8fdf1872b061

29 January 2026
|

Carrier Solutions UK was chosen to provide a rapid HVAC solution for Chichester College, where a chiller system had reached the end of its operational life. Working alongside the installing contractor, Rossair, the team delivered a fast turnaround replacement with a Toshiba Universal Smart X (USX) solution.

With minimal disruption to term-time operations a priority, Carrier was able to supply the required USX unit from stock within 48 hours.

The installation required a 140kW capacity unit to meet the demands of the college’s E Block. Key included energy efficiency, quiet operation, compatibility with existing pumps and integration with the building management system (BMS). Due to the coastal location, the system received an anti-corrosion treatment from specialist contractor Bronz-Glow UK to ensure long-term durability.

Positioned externally on a concrete base at ground level, the USX unit was installed using a crane. Careful planning overcame access challenges posed by narrow roads, ensuring on-time delivery and smooth installation. Rossair managed the mechanical works, while a third-party controls team handled BMS integration. Carrier’s commissioning and controls engineers provided technical support throughout, with two weeks of monitored performance checks following commissioning.

“The Chichester College project highlighted the real advantage of being able to supply from stock,” said Dave McSherry, Sales Director, UK&I, Carrier Solutions UK. “With Carrier able to supply the USX unit immediately, Rossair delivering a high-quality installation and coordinated commissioning support, we were able to meet urgent requirements and the college received a reliable, future-ready system without delay.”

Content continues after advertisements

“We were impressed with how quickly the new system was delivered and installed,” said Kevin White, Estates Manager at Chichester College. “The college is committed to sustainability, energy efficiency and responsible resource management and the Toshiba USX Edge supports our operational efficiency and ongoing efforts to reduce carbon emissions and our environmental impact.”

The Toshiba USX now delivers 140kW of reliable cooling for E Block, aligned with the building’s operational schedule of nine hours a day, 22 days per month. Integration with the BMS enables efficient operation and oversight by the college’s maintenance team.

Analysis of electricity consumption over two four-month periods before and after installation (from 1 July 2024 to 1 July 2025) showed a reduction of 10,882kWh per month during active hours, equating to an approximate saving of 43,528 kWh over the four-month testing period, with a cost saving of approximately £8,700.