Barkell's on-site solution

7516add3-6b9b-4aa7-9a58-67959205566c

20 August 2018
|
Air handling unit manufacturer Barkell has supplied five bespoke AHUs for a major refurbishment project at Canary Wharf in London.

10 South Colonnade was one of the original towers constructed on the Canary Wharf estate in the early 1990s, to the  the south west of the main tower and Canary Wharf DLR station.
M&E contractor Bancroft was selected for the execution of the project along with Aecom as consulting engineers from the design phase through to practical completion and handover.

Barkell was chosen  to supply replacement air handling units and, as this was a refurbishment of an older building, there were space and access restrictions which made it challenging to comply with Building Regulations Part L and the ErP (Energy-related Products Directive 2009/125/EC).

To overcome this, Barkell designed and supplied the  AHUs in flat-pack form and they were built on site by Barkell engineers.

The solution
  • Manufacture and supply of 5 bespoke AHUs
  • Evaporative humidification
  • Site leakage testing to DW 143 standards
  • Casing constructed to BS EN1886 T2 thermal transmittance and TB2 thermal bridging standards

Steve Lockwood, principal engineer, Aecom, said: "The main issues on this project were fitting the AHUs in tight areas and late change requirements. However, Barkell overcame these by putting forward multiple configuration options during the design phase, and adapting to updated requirements.

"With limited access routes to the created plant rooms,  Barkell’s ability to construct on site was also very important on this project.

"Overall, we were very impressed with the build quality, and all units commissioned have had no issues in terms of meeting design performance.”

www.barkell.co.uk
Content continues after advertisements